   Compression check in engine cylinders
   Engine check by means of the vacuum gage
   Removal and installation of a cover of an impellent compartment from the bottom
   + 4-cylinder petrol engines
   + 6-cylinder petrol engines
   - Diesel engines
      Removal and installation of the top cover of the engine
      Installation of the piston of the first cylinder in situation VMT
      Removal and installation of a cover of a head of cylinders
      Removal and installation of a head of cylinders
      Removal and installation of a forward cover
      Removal and installation of the top directing chain
      Replacement of chains of a drive of GRM and installation of phases of a gazoraspredeleniye
      Removal and installation of camshafts
      Removal and installation of an intermediate asterisk
      Removal and installation of a natyazhitel of a chain
      Removal and installation of a maple belt
   + System of greasing of the engine
+ cooling and heating Systems
+ Power supply system and release
+ engine Electric equipment
+ Manual transmission
+ Automatic transmission
+ Coupling and power shafts
+ Brake system
+ Suspension bracket and steering
+ Body
+ Onboard electric equipment






Removal and installation of a forward cover

Removal

 PERFORMANCE ORDER

1. Uncover heads of cylinders.
2. Turn out a natyazhitel of a chain.
3. Remove the toplivopodkachivayushchy pump.
4. Disconnect a forward cover.
5. Raise a stopper of the top directing. The top directing does not act in film.
6. Remove forward a forward cover.


Installation

 PERFORMANCE ORDER

1. Clear interfaced surfaces on a forward cover and an adjacent surface.

2. Put in the form of the roller in thickness of 1.5 ± 0.5 mm hermetic (1), as is shown in an illustration. As hermetic it is possible to apply Loctite-5900.

3. Establish a forward cover (2) and fix it the moment 14Нм. Thus fix also the holder of an electric wire of the valve of shutdown.

 Cover fix during 10 mines after hermetic drawing. Hermetic do not smear.

4. Establish the pump of preliminary supply of fuel.
5. Establish a natyazhitel of a chain with a new sealing ring.
6. Establish a cover of a head of cylinders.